Progress Update – November 2023
- Successfully removed all scaffold from the houses, providing unobstructed views and a clear picture of the progressing structures.
- Ongoing first-fix electrical and plumbing, with completion on Plot 1 & 2, a crucial step towards functional interiors.
- Continued internal insulation and boarding, shaping the framework for comfortable living spaces.
- Ongoing internal plastering, adding the next key stage to the interior aesthetics.
- Advancing groundworks to set levels at the front of the property, enhancing the overall landscape.
- Despite grappling with winter weather and shorter daylight hours, the team perseveres, ensuring the project remains on course.
Works in Next Period:
- Aiming to complete plastering in Plot 1, a pivotal step towards finalising the interior spaces.
- Continuing internal boarding and insulation work across all plots, maintaining momentum in construction.
- Focusing on the completion of lower ground floor tanking systems.
- Installation of staircases in all plots
- Hardcoring and compacting external areas to prepare for the next phases of external construction.
- Achieving the completion of the stone face of the retaining wall.
- Anticipating the installation of windows and front doors, a significant step towards sealing the homes.
Progress Update – October 2023
Project Update: Holmfirth Road, Holmfirth – Three Detached Houses
Works Completed to Date (October):
- Successfully concluded roofing structure on all plots, marking a key milestone in structural development.
- Commenced internal roof insulation and internal boarding for enhanced function
- Started first-fix plumbing and electrical work.
- Scaffold dropped on Plot 1, providing improved visibility of the ongoing construction.
- Progressing towards scaffold removal on all plots.
- Continued lower ground floor tanking.
Works in Next Period:
- Expected completion of scaffold removal on all plots for unobstructed views.
- Advancing first-fix plumbing and electrical work to support the functional aspects of each home.
- Continuing internal boarding, with plans to initiate plastering, shaping the interior spaces.
- Progression of external works, beginning the levelling of external works to enhance the surrounding landscapes.
Progress Update – September 2023
Project Update: Holmfirth Road, Holmfirth – Three Detached Houses
Works Completed to Date (September):
- Plot 1 (Oakbrooke)
- Successfully completed roofing, enhancing both structure and aesthetics.
- Installed Velux windows for natural light and architectural flair.
- Plot 2 (Heatherbell)
- Commenced roofing, with completion expected in the coming weeks
- Completed installation of elegant cills, elevating Heatherbell’s exterior.
- Plot 3 (Meadow Vale)
- Started roofing, on track for completion in the coming weeks.
- Completed installation of cills, adding character to Meadow Vale.
- General Developments:
- Initiated K11 tanking on the lower ground floor for structural resilience.
- Installed tin walls on the ground and first floor, enhancing external aesthetics.
- Completed cill installation across all plots for functional and design cohesion.
Works in Next Period:
- Completing roofing across all plots for overall project elevation.
- Finalizing internal tin walls across all plots, forming the rooms
- Commencing first-fix electrical and plumbing work, laying the groundwork for interior installations.
Progress Update – August 2023
Project Update: Holmfirth Road, Holmfirth – Three Detached Houses
Works Completed to Date (August):
- Progress remains on schedule as we advance with our development.
- Roof trusses have been successfully installed on Plot 1 (Oakbrooke), and our skilled joiners are making excellent progress on the traditional roof elements.
- Plot 2 (Heatherbell) has seen the completion of first-floor joists and boarding. External walls followed, and the structure is now ready for trussed roofs.
- Plot 3 (Meadow Vale) has achieved first-floor joists and boarding completion, with external walls advancing toward the wall plate for the roof truss installation.
- Internal partition walls in each plot are taking shape, giving these homes their unique character and layout.
- Our attenuation system is now fully installed.
- Foul drainage systems have been successfully installed in all plots. Additionally, the upper-floor slabs have been poured in each plot, setting the stage for further progression of the internals
Works in the Next Period:
- The next phase involves the continuation of roof formation, including truss roofs, felting, slating, and preparing for the installation of the PV system on each plot.
- Final stonework required at the gables will be completed to add that finishing touch.
- We are set to commence the tanking system in preparation for the underfloor heating system installation.
- Anticipated commencement of the first fix plumbing works to ensure all systems run smoothly.
- Our team will be busy measuring up and placing orders for the windows to enhance the aesthetics and energy efficiency of these homes.
- Gas connections will be completed
Progress Update – July 2023
Project Update: Holmfirth Road, Holmfirth – Three Detached Houses
Works Completed to Date (July):
- We are pleased to report that the development is progressing as planned, and we are on schedule with our timeline.
- The stonework on each house is advancing splendidly, showcasing the exquisite Yorkshire stone, enhancing the aesthetic appeal of the properties.
- Plot 1 (Oakbrooke) has achieved a significant milestone with the successful installation of first-floor joists.
- Plot 2 (Heatherbell) is scheduled to have its first-floor joists installed during week commencing 31st July, with Plot 3 (Meadow Vale) following a week later.
- As part of our commitment to sustainability, we have partnered with local PV supplier, Northern Renewables, to provide a PV package for each plot. This environmentally friendly initiative allows the houses to generate their own sustainable energy.
- Roof construction is set to commence towards the end of August, paving the way for the subsequent phase – the internal fitout.
- Our dedicated team is working tirelessly to ensure top-notch workmanship throughout the construction process.
Please note: These properties are now live on Simon Blyth, and you can contact their Holmfirth office for viewings and site visits. Don’t miss the chance to experience the allure of these homes firsthand!
Works in the Next Period:
- Our focus for the upcoming period is to bring the superstructure up to the wall plate, which includes the installation of structural steels.
- We will be finalising the drainage installation, commencing the attenuation tank installation, and shaping stepped gardens to enhance the landscape.
- The roof trusses will be delivered to the site, marking the commencement of the roof installation phase.